T. H.169 IMPROVEMENTS

/, T.H. 169/T. H.169 IMPROVEMENTS

T. H.169 IMPROVEMENTS

 

DECEMBER 4, 2017

The HWY 169 construction crews have begun building the retaining walls for the pedestrian underpass.  The attached image depicts the construction of the aggregate base.  Upon completion of this work, the footings for the wall will be installed.  Other work on the project includes the construction of storm sewer pipe extending from the Mississippi River to the highway along East River Entry.  Traffic detours will remain as they currently are being utilized to complete this work.

  If you have any questions, please feel free to the hotline at 763-231-4842. Tim Hanson the City Engineer can also be reached at 763-923-7105

Project Layout Map 2

DECEMBER 1, 2017

The HWY 169 construction crews have begun building the retaining walls for the pedestrian underpass.  The image above depicts the construction of the aggregate base.  Upon completion of this work, the footings for the wall will be installed.  Other work on the project includes the construction of storm sewer pipe extending from the Mississippi River to the highway along East River Entry.  Traffic detours will remain as they currently are being utilized to complete this work.

NOVEMBER 17, 2017

The T.H. 169 project temporary lanes, located north of Elm Creek, were constructed this past weekend (November 17th, 18th, & 19th). The relocating of traffic to these temporary lanes will allow underground construction to be completed along the south side of T.H. 169. This roadway alignment will remain in place until the spring of 2018.

If you have questions or comments call the Champlin Project Hotline at 763-231-4842.


West River Road was closed on Monday, October 23, 2017 from Hennepin Landing northwest to Trunk Highway 169.  The road will remain closed until next summer.  The detour route is Hayden Lake Road to TH 169.


2018-01-05T13:13:39+00:00